A9 Dualling Light Bg
Login / Register icon Register Login
A9 Dualling
A9 Engage
Overview
Sections
News
Roadworks
Delivery Plan
Social Value
A9 Dualling A9 Engage
A9 Dualling
Overview Sections News Roadworks Delivery Plan Social Value
Home > A9 Dualling > Roadworks > A9 Tomatin to Moy - A9 realignment at Tomatin

Traffic management changes – A9 realignment at Tomatin

Update: Due to weather, these works have been rescheduled

Due to poor weather conditions, Overnight temporary traffic signals and convoy system will now be in place on the A9 south of the Tomatin north junction for approximately five days from 24 November. From 28 November, both lanes of the A9 will be temporarily realigned until Autumn 2026.

The existing access junction to Tomatin will be closed from 5 December with a temporary access junction for residents becoming operational.

We may require to change these dates further due to poor weather conditions. This page will be updated regularly.

 

Location

On the A9 near Tomatin.

Description

Overnight temporary traffic signals and convoy system will be in place on the A9 south of the Tomatin north junction for approximately five days from 24 November 2025. Road users will be stopped at temporary traffic signals and a convoy system will guide them through the works area. 

These works are required to allow the workforce to safely undertake works to temporarily realign the A9.

From 28 November 2025, both lanes of the A9 will be temporarily realigned at Tomatin to facilitate the construction of a new underpass at Tomatin, with the realignment expected to remain in place until Autumn 2026. 

The existing access junction to Tomatin will also be closed from 5 December, with a new temporary junction for Tomatin residents and visitors becoming operational from this date located approximately 400 metres south of the existing junction. The new junction will be clearly signposted.

The maps below illustrates the realignment and location of the new junction:

A map of a road

AI-generated content may be incorrect.

 

 

A map of a road with text

AI-generated content may be incorrect.

Date and time:

The overnight traffic signals will be in place for approximately five days from Monday 24November 2025 between the hours of 1900 and 0600 each evening. There will be no work carried out on Sunday nights.

The realignment will be operational from 28 November and new temporary access junction will be operational from 5 December and will remain in place until Autumn 2026.  

Back to works and traffic
Contact Terms and Conditions Accessibility